Quick Updates & New timelines for Masjid Construction

posted Apr 14, 2013, 6:11 AM by Islamic Society Ballarat

Assalam-o-Alaikum,


Following are the status updates and timelines for the construction of Masjid:

 

ü  Detailed Elevation Plan has been developed and submitted to City Council.

ü  On the basis of detailed elevation plan we are receiving quotes from different builders.

ü  Planning Permit for new construction has been submitted 4 months ago and still waiting for the council approval. Expected time left is another three to four weeks.

ü  After getting planning permit for new construction, we will apply for building permit and the expected time for getting building permit from city council is 60 days.

ü   Soil test has already ordered and the expected time for soil test report is the end of April-2013.

Jazakallah Khar for all your support so far and please pray to Allah Subhanau Ta'allah that the construction of masjid starts asap.