Construction Updates

Second Progress Payment

posted Mar 11, 2014, 6:24 AM by Islamic Society Ballarat   [ updated Mar 11, 2014, 6:24 AM ]

Second Progress Payment paid to Builder of $ 13,450.

Construction / Foundation Started

posted Mar 9, 2014, 9:12 AM by Islamic Society Ballarat   [ updated Mar 9, 2014, 9:12 AM ]

Mashallah Builder is going very fast. He have Started digging site for Masjid Foundation and iron structure in foundation is ready.

Shed demolished for Praying hall

posted Mar 9, 2014, 9:07 AM by Islamic Society Ballarat   [ updated Mar 9, 2014, 9:07 AM ]

The builder has demolished the shed to prepare site for construction.

Contract Signed With Builder

posted Mar 9, 2014, 8:50 AM by Islamic Society Ballarat   [ updated Mar 11, 2014, 6:22 AM ]


Contract is signed with builder of about $134,000.
Builder Hope Building Construction Will Complete in four Months
A checque of $ 6725 as 5 % down payment given to builder.